Nigeria;s TCN commissions Damaturu substation

TCN has commissioned the 330/132 kV transmission substation in Damaturu, 12 years after a local contractor failed to complete the project. The contract, which was awarded back in 2006, was scheduled to be completed within 18 months. However, the project experienced delays until TCN took over the project. The project was then handed over to the TCN task team about two months ago for completion.