BRPL completes electrification work at world’s largest Covid care centre in record time

BSES Rajdhani Power Limited (BRPL) has completed the electrification works at the world’s largest Covid care centre in record time to ensure seamless power supply.

Over 100 workers and officials of BRPL worked round the clock to install 22 km of underground cables and 24 transformers for handling a load of 23 MW. The electrification work was completed in a record time of nearly 15 days. Initially, BRPL had been entrusted with providing an electricity supply load of 18 MW, but the power load was subsequently increased to 23 MW looking at the requirements.