ANDRITZ to supply electro-mechanical equipment for Kutehr hydropower plant

ANDRITZ has received a contract from JSW Energy (Kutehr) Limited to supply the electro-mechanical equipment for the 240 MW Kutehr hydroelectric plant located on the river Ravi in the Chamba district of Himachal Pradesh.. .

The plant will generate approximately 955 GWh of power, thus supplying clean and renewable energy to around 4.6 million households. The contract includes design, manufacturing, supply, transport, erection, testing and commissioning of three Francis turbine generator units with a capacity of 80 MW each, along with associated auxiliaries and ancillary equipment.

 