Powergrid advances work on 400 kV Silchar–Misa line in Assam

Powergrid has charged eight gas-insulated switchgear (GIS) bays of a 400 kV substation in Misa, Assam. …

The substation was constructed by KEC International, under the larger North Eastern Region Strengthening Scheme-II (NERSS-II). Some of the key components of the NERSSII project include the 132 kV Biswanath. Chariyalli–Itanagar, and the 400 kV Silchar–

Misa and Surajmaninagar–P.K. Bari lines, with associated line bay extension works. It also involves the construction of the 400/132 kV Surajmaninagar and P.K. Bari substations. Earlier in November, Powergrid had charged the 400 kV Silchar substation. The advancement on the Misa substation brings the 400 kV Silchar–Misa line closer to full energisation.