NTPC commissions fourth unit of Kameng hydroelectric project

The fourth unit of 150 MW capacity of the 4×150 MW Kameng hydroelectric project of NTPC Limited’s subsidiary, North Eastern Electric Power Corporation Limited is commercially operational.

Unit-1 and 2 of the project were commissioned in June and July 2020 respectively, while unit 3 was commissioned in January 2021. With this, the commissioned and commercial capacity of NTPC group has become 64,075 MW.

 