Oriano mulling towards commissioning of first phase of captive solar project for Hira Group, Chhattisgarh

Oriano has announced that it has won an order for one of the largest captive solar project under commercial and industrial (C&I) segment in Chhattisgarh.

The total project capacity accumulates to 168 MWp and the first phase of 70 MWp will be commissioned by mid-April 2022 to be evacuated at 132 kV. The balance capacity execution has already started and targeted to be commissioned by October 2022. Theproject is on captive capex open access mechanism. Oriano is executing the project with turnkey scope of development, engineering, procurement, construction, commissioning and operation and maintenance for five years.