Suzlon Group has secured a significantly large order for its 3 MW series of wind turbines from Serentica Renewables.
Suzlon will install 68 wind turbine generators with a hybrid lattice tubular tower and a rated capacity of 3 MW each for Serentica’s 204 MW wind power project coming up at Koppal in Karnataka. Suzlon will supply the wind turbines (equipment supply) and execute the project including erection and commissioning, besides providing comprehensive operation and maintenance services post‐commissioning. The project is expected to commission by early 2024.