K.P. Energy Limited has commissioned 25.2 MW (Phase-III) interstate transmission system (ISTS) connected wind power project at Sidhpur site in Devbhoomi Dwarka, Gujarat.
The project comprises of 12 wind turbine generators of 2.1MW each. The Phase-III commissioning is a part of the 250.8 MW ISTS connected wind power project capacity awarded to Apraava Energy Private Limited by Solar Energy Corporation of India Limited under Tranche-VIII bidding. With the present Phase-III commissioning, the net cumulative capacity commissioned at Sidhpur site stands at 107.10 MW (i.e. 52.5 MW + 29.4 MW + 25.2 MW) against the awarded capacity of 250.8 MW.