Apraava Energy secures new transmission project in Madhya Pradesh

Apraava Energy Private Limited has secured a bid for a new interstate transmission project in Madhya Pradesh through tariff-based competitive bidding (TBCB) process. The project involves the construction of approximately 40 kilometers of 765 kV double-circuit transmission lines, alongside the establishment of a 3,000 MVA substation. Apraava will spearhead the project’s development utilizing the build, own, operate, and transfer model. The stipulated completion timeframe of 24 months from the date of special purpose vehicle  transfer underscores Apraava’s commitment to timely execution.

The primary objective of this project is to cater to the increasing power needs of the state, aligning with broader efforts to bolster energy infrastructure and address escalating demand.