Bharat Heavy Electricals Limited (BHEL) has received a letter of intent (LoI) from Damodar Valley Corporation (DVC) for the steam generator island package of the 2×660 MW Raghunathpur Thermal Power Station (TPP) Phase-II project in Purulia district, West Bengal.
The scope of work includes the supply, erection, testing, and commissioning of steam generators and auxiliaries, electrostatic precipitators, flue gas desulphurisation systems, ash handling systems, and associated electrical and control and instrumentation works. Additionally, the contract covers civil works for the project. The project was awarded through international competitive bidding, with an estimated contract value of approximately Rs 62 billion. The execution timeline for the completion of facilities is set at 48 months and 52 months for the respective units.