L&T Heavy Engineering dispatches steam generator for GHAVP

L&T Heavy Engineering has dispatched the first steam generator for Units 3 and 4 of the Gorakhpur Haryana Anu Vidyut Pariyojana (GHAVP) in Fatehabad , Haryana.

The steam generator was delivered seven months ahead of schedule and is the first of four being manufactured by L&T for GHAVP. Units 3 and 4 are part of Nuclear Power Corporation of India Limited’s ten 700 MW pressurised heavy water reactors under construction in fleet mode across the country. With this, L&T has so far supplied five steam generators for the 10 x 700 MW programme.