NLC commissions 106 MW of 300 MW Rajasthan solar project

NLC India Limited has commissioned the second phase of its 300 MW solar power project at Barsingsar in Bikaner district, Rajasthan.

The latest commissioning of 106 MW was declared commercially operational following the receipt of the commissioning certificate from the Rajasthan Renewable Energy Corporation Limited. With this, the total operational capacity of the project stands at 158.83 MW. Earlier, the first part of the project, with a capacity of 52.83 MW, was declared commercially operational on August 26, 2025. The remaining capacity is expected to be commissioned in subsequent phases.