The Transmission Company of Nigeria (TCN), Nigeria’s state-owned TSO, has completed live line maintenance on the 132 kV Zaria–Funtua transmission line without interrupting bulk power transmission.
The maintenance was carried out by TCN’s Kaduna Region Live-Line Crew from July 4 to July 7, 2026, under energised conditions, eliminating the need for a planned outage.