Tata Power commissions 400kV Jalpura-Khurja transmission corridor

Tata Power Company Limited has commissioned the second element of its Jalpura-Khurja Transmission Project in Uttar Pradesh. This enhances connectivity to the growing electricity demand centres across NCR and Western Uttar Pradesh.

Executed through TP Jalpura Khurja Power Transmission Limited, a wholly owned subsidiary of Tata Power, the second element comprises a 400 kV double-circuit transmission line from Khurja to Jalpura spanning 162 circuit kilometres (CKM) and a 400/220 kV GIS substation at Jalpura with 1,000 MVA transformation capacity. The 162 CKM transmission corridor comprises two circuits of approximately 81 km each and establishes a critical high-voltage link between Khurja and Jalpura. Tata Power’s transmission portfolio now stands at 7900 circuit kilometres of lines operational and under execution across India.