The renovation and modernisation (R&M) and life extension (LE) of a TPP is a cost-effective way of generating additional power from the existing units at a lower cost and in less time. The R&M of a plant increases its operational efficiency and enhances power generation. The R&M programme aims to install the latest technology, equipment and systems at TPPs to enhance their efficiency, reliability and output, and optimise their operation and maintenance (O&M) reÂquirements. It also defers the construction of new power plants and saves on capex along with resolving issues of land acquisition and compensation. The obÂjective of R&M is not just to help the plant regain lost efficiency, but also to improve environmental performance and output reliability of the plant.
Recently, GE Power India Limited along with its affiliates, in consortium with NGSL, completed its steam turbine R&M project at NTPC’s Ramagundam super thermal power station. It led to a reÂmarÂkable improvement of 9.9 per cent in the turbine heat rate and exÂteÂnÂded the turbine life by 20 years. This led to an average improvement of 3.8 per cent in the thermal efficiency of Units 1 and 3. The upgraded units are capable of supporting 0.212 million metric tonnes per year potential annual savings in coal consuÂmÂption while also reducing CO2 emissions.
Growth drivers
The R&M programme aims to mitigate problems arising due to generic defects and design deficiencies, inefficient opeÂration, obsolescence of equipment and replacement of equipment in case of unforeseen failures; and help meet the environmental norms for PM, SO, NOx, mercury and water consumption. For each plant’s specific need, there are different R&M alternatives.
R&M programme, LE and uprating: In this process of R&M, the focus is on eqÂuipment facing fatigue stress and creep because of high temperatures. This includes turbine rotors and casings, HP pipings, boiler headers, boiler drums, main steam piping and valves. A residual life assessment (RLA) study using non-destructive and destructive tests helps estimate the remaining life of critical components and helps determine measures to extend the life of those components, sometimes even up to 15-20 years. An RLA study can be carried out after 100,000 hours of operation if the need arises. Under this programme, examinations to determine viable alternatives for modernisation are conducted. The timely adoption of specific technologies can increase output and efficiency.
R&M programme for meeting environment norms: With the introduction of tightened environmental norms, the scope of the R&M programme, which was earlier limited to the upgradation of electrostatic precipitators for particulate matter control, has been expanded to controlling SOx and NOx emissions. TPPs require installation of flue gas desulphurisation systems, combustion optimisation and retrofitting at the units to tackle SOx and NOx emissions. The need to reduce water consumption in TPPs along with the shift to biomass co-firing has created opportunities for the R&M of TPPs.
R&M programme for flexibilisation: Plants need flexibilisation to deal with the intermittency of renewable energy generation. The flexibilisation of power plants has been picking up pace, and needs sophisticated automation and refurbishment of boilers, turbines and mills. SynÂchronised IoT-based technology is needed to monitor the cyclic load variation and control the start-stop operation. To iniÂtiate the process, certain stuÂdies and tests need to be conducted on thermal units in order to determine how the minimum load can be reduced and ramp rate can be improved. These studies help determine the necessary measuÂrements for the optimisation of existing controls. Thermal feasibility study and streÂss anaÂlyÂsis are the key processes inÂvolved in flexiÂbilisation. Based on these examinations, the condition monitoring system can be installed and the control and insÂtruÂmentation system can be upgraded, etc.
Progress in R&M of TPPs
A total of 654 units, with an aggregate capacity of over 81 GW, have undergone R&M/LE works since 1985. During 2012-17, R&M/LE works were carried out at 7,200 MW of units as compared to 17,000 MW during 2007-12.
The Central Electricity Authority (CEA) had identified 71 units with an aggregate capacity of 14,929 MW for R&M/LE worÂks for the period 2017-22. For LE works, a total of 34 units (aggregating 7,570 MW) have been identified in the state sector; and for R&M works, 30 units (7,135 MW) have been identified in the state sector and seven units (224 MW) in the central sector. Up to June 2022, a total of seven unÂits comprising a capacity of 997 MW underwent R&M/LE woÂrks under the programme. These included units owned by NEEPCO (Kathalguri CCGT), Gujarat State ElectriÂcity CorpoÂraÂtion Limited (Ukai and Wankabori stations), Mahagenco (Koradi station), Uttar Pradesh Rajya Vidyut Utpadan Nigam (Obra station) and NTPC Limited (Barauni station).
Issues and challenges
The planning, management and implementation of R&M projects come with numerous issues. There have been delaÂys in target completion due to the slow supply of materials, which leads to exÂtenÂded shutdowns. While a large number of TPPs units require R&M/LE works, it comes at a cost of power plant downtime leading to power shortages. With the ever-growing demand, competitive intensity is inÂcreasing, creating a heavy burden on the supply side. Even though Ministry of Power is actively taking measures to promote R&M projects, the rate of implementation remains slow. The scarcity of funds with power plant developers and opÂerators, and lack of investor confidÂeÂnce in R&M projects add to the challenÂges. There are also technical performance problems such as blackouts, traÂnsmissÂiÂon and distribution losses, and low acÂcess rates.
The aforementioned issues call for a new approach towards the implementation of R&M/LE works, which require accurate identification of plant-specific R&M options, realistic time schedules and increased participation from executing agencies.
Most of the utilities approach the R&M programme in two ways. The first apÂproach involves setting up a plan with the scope of work outlined on the basis of condition assessment, plant operation data and feedback from O&M engineers. The set of activities is then enlisted and implemented, minimising downtime and generation loss, but often the benefits from the process are limited. The second approach involves the implementation of a comprehensive scheme in one tranche after ensuring adequate input supply. The benefits of the process are definable and quantifiable.
The government has been watchful of the delays experienced in various R&M projects. The government recommends setting up dedicated R&M teams by the utilities to improve the efficiency of R&M works, reducing the time gap betÂween DPR and RLA studies. The goverÂnÂment suggests that financing for R&M/ LE works should be sourced beforehand to avoid delays.
Net, net, R&M has been recognised as one of the most cost-effective options to increase power generation and imÂpÂrove compliance with environmental norms. When coupled with the LE programme for old thermal power units, it can increase their useful life by 15-20 years, beyond the original design’s economic life.
